JOB-0088Ilves Metalli Oy
Customer CUS-008 · Completed · opened 18.03.2026 at 10:13 · completed 06.05.2026 at 10:13
Work centres: CNC-1, CNC-2, WELD-1
No blocking findings: the margin is reportable.
Quote basis and actual
| Item | Quote basis | Actual |
|---|---|---|
| Revenue (allocated) | 37 038,19 € | 37 038,19 € |
| Material | 14 190,53 € | 13 776,56 € |
| Labour | 177,46 h × 69,57 €/h | 10 370,81 € |
| Subcontract | 0,00 € | 0,00 € |
| Other variable costs | 0,00 € | 0,00 € |
| Margin | — | 12 890,82 € |
The estimated margin is not a stored figure: the quote basis stores the items, and the bridge sets out the difference between estimated and actual line by line.
Snapshot computed 21.09.2026 at 14:48 · definition job-margin/2026-09-20.1 · inputs 25e9486ae124
The margin bridge
The bridge explains the arithmetic difference: each line says how much of the gap between the estimated and the actual margin that driver accounts for. It does not establish a cause. Why a price or an hours figure moved is a different question, and this view does not answer it.
- 1Revenue differencerevenue_varianceNo claim0,00 €
No claim A zero line points at no source rows: it claims nothing, so no evidence is to be expected.
- 2Material quantity differencematerial_quantity_varianceCausal+486,56 €
Evidence (8 rows · Causal reference: 8)
Causal referenceThe rows that produced the amountThese rows produced the amount: every figure is computed from these rows.
Table Source Row Version Time (UTC) Mapping Quality Field Material consumption material_consumption erp MC-000703 1 27.04.2026 at 16:19 synthetic/v1 In order qty Material consumption material_consumption erp MC-000704 1 19.03.2026 at 12:17 synthetic/v1 In order qty Material consumption material_consumption erp MC-000705 1 03.05.2026 at 01:13 synthetic/v1 In order qty Material consumption material_consumption erp MC-000706 1 12.04.2026 at 16:47 synthetic/v1 In order qty Material consumption material_consumption erp MC-000707 1 02.04.2026 at 11:42 synthetic/v1 In order qty Material consumption material_consumption erp MC-000708 1 11.04.2026 at 18:27 synthetic/v1 In order qty Material consumption material_consumption erp MC-000709 1 19.04.2026 at 05:25 synthetic/v1 In order qty Material consumption material_consumption erp MC-000710 1 23.03.2026 at 23:43 synthetic/v1 In order qty - 3Material price differencematerial_price_varianceCausal−72,63 €
Evidence (8 rows · Causal reference: 8)
Causal referenceThe rows that produced the amountThese rows produced the amount: every figure is computed from these rows.
Table Source Row Version Time (UTC) Mapping Quality Field Material consumption material_consumption erp MC-000703 1 27.04.2026 at 16:19 synthetic/v1 In order unitCost Material consumption material_consumption erp MC-000704 1 19.03.2026 at 12:17 synthetic/v1 In order unitCost Material consumption material_consumption erp MC-000705 1 03.05.2026 at 01:13 synthetic/v1 In order unitCost Material consumption material_consumption erp MC-000706 1 12.04.2026 at 16:47 synthetic/v1 In order unitCost Material consumption material_consumption erp MC-000707 1 02.04.2026 at 11:42 synthetic/v1 In order unitCost Material consumption material_consumption erp MC-000708 1 11.04.2026 at 18:27 synthetic/v1 In order unitCost Material consumption material_consumption erp MC-000709 1 19.04.2026 at 05:25 synthetic/v1 In order unitCost Material consumption material_consumption erp MC-000710 1 23.03.2026 at 23:43 synthetic/v1 In order unitCost - 4Labour hours differencelabour_hours_varianceCausal+1 975,09 €
Evidence (15 rows · Causal reference: 15)
Causal referenceThe rows that produced the amountThese rows produced the amount: every figure is computed from these rows.
Table Source Row Version Time (UTC) Mapping Quality Field Time entry time_entry timeclock TE-001311 1 30.04.2026 at 01:27 synthetic/v1 In order hours Time entry time_entry timeclock TE-001312 1 11.04.2026 at 23:07 synthetic/v1 In order hours Time entry time_entry timeclock TE-001313 1 18.03.2026 at 16:01 synthetic/v1 In order hours Time entry time_entry timeclock TE-001314 1 16.04.2026 at 13:03 synthetic/v1 In order hours Time entry time_entry timeclock TE-001315 1 20.04.2026 at 17:24 synthetic/v1 In order hours Time entry time_entry timeclock TE-001316 1 19.04.2026 at 06:55 synthetic/v1 In order hours Time entry time_entry timeclock TE-001317 1 24.04.2026 at 14:22 synthetic/v1 In order hours Time entry time_entry timeclock TE-001318 1 08.04.2026 at 20:35 synthetic/v1 In order hours Time entry time_entry timeclock TE-001319 1 28.04.2026 at 19:03 synthetic/v1 In order hours Time entry time_entry timeclock TE-001320 1 28.03.2026 at 13:59 synthetic/v1 In order hours Time entry time_entry timeclock TE-001321 1 18.04.2026 at 16:11 synthetic/v1 In order hours Time entry time_entry timeclock TE-001322 1 20.04.2026 at 18:37 synthetic/v1 In order hours Time entry time_entry timeclock TE-001323 1 08.04.2026 at 23:03 synthetic/v1 In order hours Time entry time_entry timeclock TE-001324 1 22.03.2026 at 13:29 synthetic/v1 In order hours Time entry time_entry timeclock TE-001325 1 23.04.2026 at 08:37 synthetic/v1 In order hours - 5Labour rate differencelabour_rate_varianceCausal−0,01 €
Evidence (15 rows · Causal reference: 15)
Causal referenceThe rows that produced the amountThese rows produced the amount: every figure is computed from these rows.
Table Source Row Version Time (UTC) Mapping Quality Field Time entry time_entry timeclock TE-001311 1 30.04.2026 at 01:27 synthetic/v1 In order rate Time entry time_entry timeclock TE-001312 1 11.04.2026 at 23:07 synthetic/v1 In order rate Time entry time_entry timeclock TE-001313 1 18.03.2026 at 16:01 synthetic/v1 In order rate Time entry time_entry timeclock TE-001314 1 16.04.2026 at 13:03 synthetic/v1 In order rate Time entry time_entry timeclock TE-001315 1 20.04.2026 at 17:24 synthetic/v1 In order rate Time entry time_entry timeclock TE-001316 1 19.04.2026 at 06:55 synthetic/v1 In order rate Time entry time_entry timeclock TE-001317 1 24.04.2026 at 14:22 synthetic/v1 In order rate Time entry time_entry timeclock TE-001318 1 08.04.2026 at 20:35 synthetic/v1 In order rate Time entry time_entry timeclock TE-001319 1 28.04.2026 at 19:03 synthetic/v1 In order rate Time entry time_entry timeclock TE-001320 1 28.03.2026 at 13:59 synthetic/v1 In order rate Time entry time_entry timeclock TE-001321 1 18.04.2026 at 16:11 synthetic/v1 In order rate Time entry time_entry timeclock TE-001322 1 20.04.2026 at 18:37 synthetic/v1 In order rate Time entry time_entry timeclock TE-001323 1 08.04.2026 at 23:03 synthetic/v1 In order rate Time entry time_entry timeclock TE-001324 1 22.03.2026 at 13:29 synthetic/v1 In order rate Time entry time_entry timeclock TE-001325 1 23.04.2026 at 08:37 synthetic/v1 In order rate - 6Subcontract differencesubcontract_varianceNo claim0,00 €
No claim A zero line points at no source rows: it claims nothing, so no evidence is to be expected.
- 7Rework differencerework_varianceNo claim0,00 €
No claim A zero line points at no source rows: it claims nothing, so no evidence is to be expected.
- 8Other variable cost differenceother_variable_varianceNo claim0,00 €
No claim A zero line points at no source rows: it claims nothing, so no evidence is to be expected.
- 9Unexplained differenceresidual_unexplainedCausal+0,04 €
Evidence (23 rows · Causal reference: 23)
Causal referenceThe rows that produced the amountThese rows produced the amount: every figure is computed from these rows.
Table Source Row Version Time (UTC) Mapping Quality Field Material consumption material_consumption erp MC-000703 1 27.04.2026 at 16:19 synthetic/v1 In order — Material consumption material_consumption erp MC-000704 1 19.03.2026 at 12:17 synthetic/v1 In order — Material consumption material_consumption erp MC-000705 1 03.05.2026 at 01:13 synthetic/v1 In order — Material consumption material_consumption erp MC-000706 1 12.04.2026 at 16:47 synthetic/v1 In order — Material consumption material_consumption erp MC-000707 1 02.04.2026 at 11:42 synthetic/v1 In order — Material consumption material_consumption erp MC-000708 1 11.04.2026 at 18:27 synthetic/v1 In order — Material consumption material_consumption erp MC-000709 1 19.04.2026 at 05:25 synthetic/v1 In order — Material consumption material_consumption erp MC-000710 1 23.03.2026 at 23:43 synthetic/v1 In order — Time entry time_entry timeclock TE-001311 1 30.04.2026 at 01:27 synthetic/v1 In order — Time entry time_entry timeclock TE-001312 1 11.04.2026 at 23:07 synthetic/v1 In order — Time entry time_entry timeclock TE-001313 1 18.03.2026 at 16:01 synthetic/v1 In order — Time entry time_entry timeclock TE-001314 1 16.04.2026 at 13:03 synthetic/v1 In order — Time entry time_entry timeclock TE-001315 1 20.04.2026 at 17:24 synthetic/v1 In order — Time entry time_entry timeclock TE-001316 1 19.04.2026 at 06:55 synthetic/v1 In order — Time entry time_entry timeclock TE-001317 1 24.04.2026 at 14:22 synthetic/v1 In order — Time entry time_entry timeclock TE-001318 1 08.04.2026 at 20:35 synthetic/v1 In order — Time entry time_entry timeclock TE-001319 1 28.04.2026 at 19:03 synthetic/v1 In order — Time entry time_entry timeclock TE-001320 1 28.03.2026 at 13:59 synthetic/v1 In order — Time entry time_entry timeclock TE-001321 1 18.04.2026 at 16:11 synthetic/v1 In order — Time entry time_entry timeclock TE-001322 1 20.04.2026 at 18:37 synthetic/v1 In order — Time entry time_entry timeclock TE-001323 1 08.04.2026 at 23:03 synthetic/v1 In order — Time entry time_entry timeclock TE-001324 1 22.03.2026 at 13:29 synthetic/v1 In order — Time entry time_entry timeclock TE-001325 1 23.04.2026 at 08:37 synthetic/v1 In order —
- Rounding difference0,04 € of the difference between the estimated and the actual margin of JOB-0088 is inside the 0,04 € the source data's own rounding accounts for: a rounding difference, not an amount no driver can place (tolerance 185,19 €)
The stored note
tolerance 18519 minor units; pyoeristysero: 0,04 € of the difference between the estimated and the actual margin of JOB-0088 is inside the 0,04 € the source data's own rounding accounts for: a rounding difference, not an amount no driver can place (tolerance 185,19 €)
The bridge is computed from the stored snapshot. The next step is always the same: open the line's evidence and check the source rows.
Findings (0)Margin 12 890,82 € · 34,80 %
None of v0's nine rules fired for this job. That is not the same as there being nothing to look at — it means that no finding was detected on these rows.